Odda substation, Norway
2015
Scope: Commissioning and configuration of protection and control system.
Odda substation, Norway
2015
Scope: Commissioning and configuration of protection and control system.
220kV Stepnaja substation, Kazakhstan
2015
Scope:
Manufacturing of modular substations (container) with full preparation (ceiling, floor, lights, heating/cooling, cabling, emergency exits), assembling all protection, RTU, AC/DC and Scada panels and cubicles.
Configuration of the ABB and Siemens protection terminals, FAT at the Aedilis’ workshop in Lithuania.
Commissioning on site of protection and RTU terminals.
Pirttikoski 400 kV substation, Finland
2015
Scope: Commissioning and configuration of protection and control, RTU systems.
Wind farm substation Kuke 220/30kV, Finland
2015
Scope:
Design works for supplying factory drawings of combines transformer and line protection panels, communication panels. Drawings of secondary wiring – circuit diagrams and protections diagrams (220kV switchgear including SLD, 220/33kV transformer, 33kV switchgear including SLD, AC/DC panel with selectivity plan), connection diagrams (220 kV switchgear, 220/33kV transformer, 33kV switchgear, AC/DC panel), cable and signal list.
Assembling of protection, telecommunication panels and marshalling boxes.
Configuration of 220kV transformer diff protection, 220kV transformer feeder protection and 33kV line and incoming feeder protection.
FAT – 220kV cubicles
SAT – 220kV transformer bay, 33kV and AC/DC panels
Neste Oil Oy substation, Finland
2015
Scope: Commissioning and configuration of protection and control system.
Vagle substation, Norway
2014
Scope: Team of engineers did RTU and HMI configuration and testing, protection complex testing during SAT, configuration of ruggedcom devices.
Aland 110kV Tellholm substation, Finland
2014
Scope:
Manufacturing of protection cubicles.
Commissioning on site ABB RED + REF relays and syncrocheck.
Small hydro plants, Norway
2014
Scope: RTU and relay protection and control commissioning and configuration works for various small hydropower plants.
300/66kV Odda substation, Finland
2015
Scope: Commissioning and configuration of protection and control system.
130/30 kV Bjorkhojden Substation, Sweden
2014
Scope: Commissioning and configuration of protection and control system.