Pirttikoski 400 kV substation, Finland
2015
Scope: Commissioning and configuration of protection and control, RTU systems.
Pirttikoski 400 kV substation, Finland
2015
Scope: Commissioning and configuration of protection and control, RTU systems.
Wind farm substation Kuke 220/30kV, Finland
2015
Scope:
Design works for supplying factory drawings of combines transformer and line protection panels, communication panels. Drawings of secondary wiring – circuit diagrams and protections diagrams (220kV switchgear including SLD, 220/33kV transformer, 33kV switchgear including SLD, AC/DC panel with selectivity plan), connection diagrams (220 kV switchgear, 220/33kV transformer, 33kV switchgear, AC/DC panel), cable and signal list.
Assembling of protection, telecommunication panels and marshalling boxes.
Configuration of 220kV transformer diff protection, 220kV transformer feeder protection and 33kV line and incoming feeder protection.
FAT – 220kV cubicles
SAT – 220kV transformer bay, 33kV and AC/DC panels
Neste Oil Oy substation, Finland
2015
Scope: Commissioning and configuration of protection and control system.
110/10/6/kV Altaj Substation, Kazakhstan
2014
Scope: Configuration and commissioning of RTU on site.
Vagle substation, Norway
2014
Scope: Team of engineers did RTU and HMI configuration and testing, protection complex testing during SAT, configuration of ruggedcom devices.
Severnyje Buzachi substation, Kazakhstan
2014
Scope: Configuration and commissioning of RTU and ABB Microscada.
Aland 110kV Tellholm substation, Finland
2014
Scope:
Manufacturing of protection cubicles.
Commissioning on site ABB RED + REF relays and syncrocheck.
Small hydro plants, Norway
2014
Scope: RTU and relay protection and control commissioning and configuration works for various small hydropower plants.
300/66kV Odda substation, Finland
2015
Scope: Commissioning and configuration of protection and control system.
130/30 kV Bjorkhojden Substation, Sweden
2014
Scope: Commissioning and configuration of protection and control system.